Biodiesel Wastewater Treatment Plant
Production Capacity:
180 m3/day
Key Results
- Able to reduce the chemical oxygen demand (COD) from 50000mg/L to less than 200mg/L meeting the Department of Environment’s discharge limit.
- Anaerobic tank with geomembrane system to trap biogas and release for flaring.
- Aeration tank with diffuser system to produce dissolved oxygen for efficient COD removal.
- Chemical treatment with coagulation and flocculation system and dissolved air flotation (DAF) system to reduce total suspended solid (TSS) from 800mg/l to less than 100mg/l.
Completion of anaerobic system with geomembrane
Flaring system to burn methane gas produced from anaerobic system
Central drive scrapper inside the clarifier
Install stainless steel wire ropes to lay geomembrane
Cooling tower system to reduce the temperature for influent water
Diffusers installation inside aeration tank